What makes a condo project ineligible?
Problems with the building's condition, money or use. Fannie Mae's list of ineligible projects (updated Nov 4, 2026) includes:
- Critical repairs. Repairs that significantly affect structural integrity, habitability, or the project's financial viability. Signs include material deficiencies, mold or water intrusion, advanced deterioration, and failed mandatory inspections.
- Unfunded repairs costing more than $10,000 per unit that should be done within the next 12 months.
- Special assessments tied to a critical repair that has not been fixed.
- Inspection reports. If a structural or mechanical inspection was done within three years of the lender's review, the lender must read it, and it cannot show unaddressed critical repairs.
- Litigation involving the association about structural soundness or habitability.
- Hotel-style operation, such as mandatory rental pooling or transient-style management.
- Too much single-owner control: one entity owning more than 20% of units in a project of 21 or more.
- Commercial space above 35% of the project or building.
Freddie Mac's condo FAQ takes the same line. A project that failed any local regulatory inspection is not eligible. An association may fund repairs with a special assessment or a loan, but repairs tied to structural integrity or habitability must be fully completed first. Freddie Mac also says special assessments cannot stand in for the 10% budget reserve allocation it requires.
Why does Florida condo law affect your loan?
Because it creates the reports a lender reviews, and the reserve rules shape your fees.
Milestone inspections. SB 4-D, passed in 2022 Special Session D and signed May 26, 2022 (Chapter 2022-269), created them (Florida Senate). Under the current statute, s. 553.899, a condo or co-op building three habitable stories or taller must have one by December 31 of the year it turns 30, then every 10 years. The local building agency can move that to 25 years based on local conditions such as nearness to salt water. Phase one is a visual review by a licensed engineer or architect. Phase two follows only if phase one finds substantial structural deterioration.
Structural integrity reserve studies (SIRS). Under s. 718.112(2)(g), an association must have a SIRS at least every 10 years for each building three habitable stories or taller. It covers the roof, structure, fireproofing and fire protection, plumbing, electrical systems, waterproofing and exterior painting, windows and exterior doors, and other items over $25,000 that affect those. Existing owner-controlled associations had until December 31, 2025, those with a milestone inspection due by December 31, 2026 may finish both together, and no SIRS may be completed after December 31, 2026.
Reserve funding. For budgets adopted on or after December 31, 2024, owners in an association that must have a SIRS cannot vote to spend those reserves on anything other than the listed components. Reserve contributions are part of the budget your association fee pays for.
The 2025 changes. HB 913 (Chapter 2025-175), approved June 23, 2025 and mostly effective July 1, 2025, adjusted the system (Senate summary):
- Coverage now turns on "habitable" stories.
- For budgets adopted on or before December 31, 2028, an owner-controlled association that finished a milestone inspection in the prior two years may pause or reduce reserve contributions for up to two annual budgets, with a majority of all voting interests, to pay for repairs. It must do a SIRS before resuming.
- Associations may fund required reserves by special assessment, line of credit or loan, with majority approval.
- The reserve item threshold rose from $10,000 to $25,000, adjusted for inflation.
- A resale buyer's cancellation window grew from 3 days to 7.
Deadlines in these laws have changed more than once. Verify any date that matters to your contract with a Florida attorney.
What should you ask the association before you buy?
Ask in writing, and send copies to your lender early. Under s. 718.503(2), a resale buyer is entitled, at the seller's expense, to the declaration, bylaws and rules, the annual budget and financial statement, the inspector's summary of any milestone inspection, and the most recent SIRS or a statement that none was done.
- Was a milestone inspection required? Did phase one lead to phase two? What repairs were ordered, and are permits open?
- When was the last SIRS done, and is it listed in the DBPR SIRS database? Associations must report a SIRS to the state within 45 days of completing it.
- How much goes to reserves in the current budget? Are contributions paused or reduced under the 2025 law?
- Are any special assessments approved or planned? Get the purpose, the amount per unit, and the payment schedule.
- Has the association borrowed or opened a credit line for repairs?
- Is the association in any lawsuit about the building?
- Are there rental pools or hotel-style operations?
- Has a lender reviewed the project recently, and did it pass?
How long do you have to review the documents?
On a resale, the contract must do one of two things under s. 718.503: state that you received the required documents more than 7 days before signing, or let you cancel within 7 days after you sign and receive them. Both counts exclude Saturdays, Sundays and legal holidays. Start the lender's project review in that window, not after it.
For the rest of the cost picture, see Florida closing costs for buyers and flood insurance costs in Sarasota and Manatee.
Sarasota Home Math is not a lender and is not affiliated with Fannie Mae, Freddie Mac, FHA or the Florida DBPR. This is general information, not legal advice.